Thank you. Please keep us posted on what DHL will reply for the shipment from the 10th!
They are in a meeting for the moment. Our forwarder will check later. As soon as I have the answer, I’ll tell you
Hi, I would like to know when the shipping to holland starts. Kind regards, David.
Same here, stuck from 10th April…
Which contribution ID’s are we at right now in regards to shipping?
Here is a news from our factory:
- 1K new engines arrived at the factory
- on 23rd, 1K engines should also be delivered
- After the 23rd: 200 to 300 per day
- This Saturday: 1.5K PicoPix Max should be ready for QC, then packed
Thanks for that Stefan, emailed them and got the response with survey.
yes I just sent it
Thanks a mill for the quick response
Same here. I contacted DHL and they told me my reference number does not exist. The journey continues (since mid-August) for me. Hopefully we get a clear update soon!
Any news about shipping to Denmark? My Indiegogo contribution id is 196XX (I can’t seem to find anything called a backerkit id, are those the same thing?)
Hello,
Sorry for bothering again: i just wanted to clarify something espec with the list that was provided earlier:
I got a mail on april 10 woth a tracking number, which states that instruction data for this shipment have been provided by the sender to dhl electronically…
Today on the 21/04 there is no update whatsoever on the number.
Since my package goes to luxembourg, am i under shipped or ready to be shipped?
Thanks in advance
No one answers my e-mails. I only get automatic replies. This is scam.
Great, so let’s hope we’ll have the same pace in the next weeks as well (1500 / week). This would mean that by end of May all units should be produced and shipped (not received but shipped). At least from my high-level calculations…
I still have my doubts as we had 0 QC approved items in last 2 weeks. Hopefully we have better luck this week. My Estimates are Mid to end June to cover all shipments at the moment.
For those people who are looking for a summary:
3018 - Shipped by Jan 2020 (before Shutdown)
1480 - Shipped second week of Mar 2020
1570 - Ready End March (1170 backers + 400 pre-orders) - Shipped April 12
1200 - Ready April Week 1 - Shipped April 12
0 - Ready April Week 2 - Holiday in China
0 - Ready April Week 3 - 784 Pc rejected due to QC Failed
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3550 pieces were manufactured post reopening. This means effectively current output is now around 507 pieces per week.
- 1500 - Expected to be ready this week (April Week 3)
- EU tracking numbers from April 12 shipment stil not active. This is normal and as expected. They will be live only once they reach the DE warehouse.
- 1000 Light Engines arrived at the factory, another 1000 is expected on April 23rd and then 200-300 Light Engines everyday.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Disclaimer: These calculations are based on updates shared by @Philips_Support_N
Previous Summary
So you mean to say that the flight which left on the 11th is still in the air.