Start with the High Level Summary Thread
Points considered:
- Current average output is under 600 units per week.
- Light engines are coming 200-300 everyday which a currently a roadblock in scaling up production.
- Being optimistic we can receive 300*5 = 1500 pieces per week.
- Assuming 100% success rate the expected max output is 1500 per week.
- We are currently at 8200 backers fulfilled.
- Assuming he is the first one. (14000-8200) /1500 = 3.8 weeks
- Since All AU/NZ units were shipped there will be some higher numbers fulfilled. Same goes for EU where shipment is happening
- Add a week for shipment process and another couple of weeks for delivery. (assuming deliveries are relatively normalized)
- That makes it 7 weeks. Give or take. All this doesn’t consider any new issues/holidays or COVID related restrictions.
Note: Above is speculation based on the stated assumptions and this is my expectation for my perk as i am 146xx. I am expecting to see something in end June or even early July.