General info about shipment and manufacturing

For those people who are looking for a summary:

3018 - Shipped by Jan 2020 (before Shutdown)
1480 - Shipped second week of Mar 2020
1570 - Ready End March (1170 backers + 400 pre-orders) - Shipped April 12
1200 - Ready April Week 1 - Shipped April 12
0 - Ready April Week 2 - Holiday in China
0 - Ready April Week 3 - 784 Pc rejected due to QC Failed
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3550 pieces were manufactured post reopening. This means effectively current output is now around 507 pieces per week.

  • 1500 - Expected to be ready this week (April Week 3)
  • EU tracking numbers from April 12 shipment stil not active. This is normal and as expected. They will be live only once they reach the DE warehouse.
  • 1000 Light Engines arrived at the factory, another 1000 is expected on April 23rd and then 200-300 Light Engines everyday.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Disclaimer: These calculations are based on updates shared by @Philips_Support_N